Question 1 of 2
1. Question
It is a good idea to leave the wording of the specification/statement of requirement very vague so that the tenderers have room to move in what they propose.
Question 2 of 2
2. Question
The procurement planning stage is far too early in the procurement process to conduct risk assessments and develop a risk management plan. It is better to wait until contract management as this is where most of the risks actually occur.